Case: Sponsor validation T 63
Introduction
How to react to a sponsor validation
Scope: Production or service company
Target group: Nicetoy project manager, project sponsor
Situation
In the midst of the T3 tricycle project, an important modification has just been approved by the sponsor. It is about changing the F2 brake with the F5 brake, more powerful and more secure. What should Mr. Thenose, project manager at Nicetoy do?
Challenge
Solution 1. Inform your superiors
Solution 2. Have the modification validated by the person in charge, update the documentation and then inform the relevant stakeholders.
Solution 3. Ask the customer to validate the modification
Solution 4. Inform the quality manager
Solution 5. Continue the project because the sponsor has validated the modification