Case: Sponsor validation T 63

Introduction

How to react to a sponsor validation

Scope: Production or service company

Target group: Nicetoy project manager, project sponsor

Situation

In the midst of the T3 tricycle project, an important modification has just been approved by the sponsor. It is about changing the F2 brake with the F5 brake, more powerful and more secure. What should Mr. Thenose, project manager at Nicetoy do?

 

Challenge

Solution 1. Inform your superiors

Solution 2. Have the modification validated by the person in charge, update the documentation and then inform the relevant stakeholders.

Solution 3. Ask the customer to validate the modification

Solution 4. Inform the quality manager

Solution 5. Continue the project because the sponsor has validated the modification

 

Possible answers